Single Event Record Display
× Home Crew Stats-old version Trail Stats Work Schedule Agency Report by Years Crew- Year by Year Totals Crew- Stats - XTAB Crew Accomplishments
Event#:440
Date: 2016-10-15
Agency:COSCA
Trail: COSCA Fall Work Day
Leader:Jerry Mitcham
Hours: 90
Volunteers:15
Distance:5800
Status: Completed
Regulars: 13
Casuals: 2
pdf:20161015COSCA.pdf
CSUCI: 0
Tag:
Previous Events
ID Date Leader Hours
6992019-10-19John Kross55.0
5152017-10-21John Kross58.5
4402016-10-15Jerry Mitcham90.0
3572015-10-17Jerry Mitcham45.0
Crew Member Hours
Anne Russell5.00
Barb Thomas5.00
Barry Dydyk5.00
Dave Edwards5.00
Dave Perlmutter5.00
Don Brusselars5.00
George Sherman5.00
Greg Sweel5.00
Jerry Mitcham5.00
John Kross5.00
Norm Simmonds5.00
Sharon Simmonds5.00
Virginia Grue5.00
This was the annual Conejo Open Space fall trail day event. The project was in the Western Plateau Area and covered several trails in the area. There were approximately 150 community volunteers, including 15 SMMTC volunteers. Collaborated with the COSCA Rangers and held briefings on the project. There were three general areas to work. Screamer Trail, the largest effort was to cut in a 0.5 mile new section of trail, requiring 6 crews. The Hill Canyon Connector Trail, a section of old road to be converted to single track trail requiring 3 crews. Lastly the Hawk Canyon Connector Trail a new connector trail to be cut in requiring 3 crews. Formed the volunteers into crews of ten and dispatched them to the work areas. For the “Screamer Trail”. the route had already been brushed. The volunteers cut about 0.4 mile of new bench, removing many stumps in the process. The “Hill Canyon Connector Trail” crews removed much brush, smoothed tread and installed several drains. The “Hawk Canyon Connector Trail” crews, cut in 0.1 mile of new bench, removed vegetation and smoothed the tread for 0.2 miles. Total volunteer hours: 15 Volunteers x 5 hours = 75hours Feet of trail maintained: 5,800