Event#: | 526 |
Date: | 2017-11-18 |
Agency: | State Parks |
Trail: | BBT Kiosk Projects |
Leader: | Barry Dydyk |
Hours: | 90 |
Volunteers: | 8 |
Distance: | 100 |
Status: | Completed |
Regulars: | 2 |
Casuals: | 6 |
pdf: | 20171118BBTKioskInstall.pdf |
CSUCI: | 0 |
Tag: | BBT_Improvements |
Previous Events
ID |
Date |
Leader |
Hours |
724 | 2020-02-15 | Jerry Mitcham | 21.5 |
656 | 2019-06-16 | Barry Dydyk | 44.0 |
655 | 2019-06-15 | Barry Dydyk | 150.0 |
583 | 2018-08-01 | Jerry Mitcham | 113.0 |
533 | 2017-12-02 | Jerry Mitcham | 26.0 |
526 | 2017-11-18 | Barry Dydyk | 90.5 |
Crew Member |
Hours |
Barry Dydyk | 17.50 |
Jerry Mitcham | 17.50 |
This was the first of four sub projects/ Eagle Projects in the BBT TH Improvement Effort The effort occurred over three days as follows:
Day1 (j Mitcham, B Dydyk) 1 hour
Load trucks with tools and table and Kiosk parts
Day2 ( J Mitcham, B Dydyk, S Horvath, L Stark) 9 hours
Install picnic table at Corral Canyon TH Dig holes, in rock, for kiosk legs and cement legs into ground.
Day 3 ( J Mitcham, B Dydyk, S Horvath,M Marangola, B Kuo, R Wolf, H Petcher) 7.5 hrs
Install kiosk legs at Ray Miller TH and at Danielson
Hours per person:
J Mitcham 17.5
B Dydyk 17.5
S Horvath 16.5
L Stark 9.0
M Marangola 7.5
B Kuo 7.5
R Wolf 7.5
H Petcher 7.5
In addition to the above adult effort we estimate that there were 187 hours of effort from the Boy Scouts.