Event#: | 558 |
Date: | 2018-04-21 |
Agency: | State Parks |
Trail: | ADA Trail Leo Carillo State Park |
Leader: | Jerry Mitcham |
Hours: | 78 |
Volunteers: | 13 |
Distance: | 2600 |
Status: | Completed |
Regulars: | 8 |
Casuals: | 5 |
pdf: | 20180421Camp13Trail.pdf |
CSUCI: | 5 |
Tag: | LCSP, CSUCI |
Previous Events
ID |
Date |
Leader |
Hours |
558 | 2018-04-21 | Jerry Mitcham | 78.0 |
386 | 2016-01-23 | Barb Thomas | 42.0 |
Crew Member |
Hours |
Barry Dydyk | 6.00 |
Dave Edwards | 6.00 |
Don Brusselars | 6.00 |
Greg Sweel | 6.00 |
Jerry Mitcham | 6.00 |
John Kross | 6.00 |
Norm Simmonds | 6.00 |
Sharon Simmonds | 6.00 |
Leo Carrillo State Park, Camp 13 Trail. This was a scheduled trail maintenance project, with student volunteers from CSUCI. The objective was routine trail maintenance on the Camp 13 Trail. There were 8 SMMTC volunteers and 5 CSUCI Student volunteers present. SMMTC volunteers met early. Two volunteers started work early and began brushing the trail with two gas powered brush trimmers. Met student volunteers. Conducted safety and tool talks. Hiked short distance to the trail head and began work. The student and remaining SMMTC volunteers primary task was to pick up the cuttings left by the power tools and perform any necessary lopping. Completed work. Hiked back to the meeting place... Completed the days project. Total volunteer hours: 13 Volunteers x 6 hours = 78 hours Feet of trail maintained: 2,600