Event#: | 774 |
Date: | 2020-12-05 |
Agency: | State Parks |
Trail: | Fossil Trail |
Leader: | Jerry Mitcham |
Hours: | 24 |
Volunteers: | 4 |
Distance: | 1900 |
Status: | Completed |
Regulars: | 4 |
Casuals: | 0 |
pdf: | 20201205FossilTrail.pdf |
CSUCI: | 0 |
Tag: | PMSP |
Previous Events
ID |
Date |
Leader |
Hours |
774 | 2020-12-05 | Jerry Mitcham | 24.0 |
773 | 2020-11-28 | Barry Dydyk | 62.0 |
768 | 2020-11-14 | Jerry Mitcham | 20.0 |
677 | 2019-08-03 | George Sherman | 6.0 |
671 | 2019-07-31 | George Sherman | 18.0 |
670 | 2019-07-28 | George Sherman | 6.0 |
668 | 2019-07-23 | George Sherman | 6.0 |
667 | 2019-07-22 | George Sherman | 6.0 |
666 | 2019-07-21 | George Sherman | 5.5 |
665 | 2019-07-14 | George Sherman | 7.0 |
664 | 2019-07-13 | George Sherman | 7.0 |
663 | 2019-07-07 | George Sherman | 4.0 |
662 | 2019-07-06 | George Sherman | 6.0 |
624 | 2019-02-10 | George Sherman | 3.0 |
555 | 2018-04-11 | Norm Simmonds | 48.0 |
550 | 2018-03-14 | Norm Simmonds | 72.0 |
546 | 2018-02-14 | Norm Simmonds | 42.0 |
367 | 2015-12-05 | Barry Dydyk | 60.0 |
307 | 2015-03-14 | George Sherman | 36.0 |
304 | 2015-02-28 | John Kross | 84.0 |
276 | 2014-11-29 | Dave Edwards | 24.0 |
189 | 2013-11-30 | Dave Edwards | 42.0 |
108 | 2012-12-29 | | 15.0 |
Crew Member |
Hours |
Anne Russell | 6.00 |
Barry Dydyk | 6.00 |
Dave Perlmutter | 6.00 |
Jerry Mitcham | 6.00 |
This was one of the specially scheduled COVID-19 trail maintenance projects. The goal of this project was to perform routine trail maintenance on the Fossil Trail. We had 4 volunteers for the project. Met at the trail head at Wendy Drive and Potrero Road. Carpooled to the Fossil Trail trailhead in Sycamore Canyon. Began work where we left off last week. Used the power tool to trim brush back to the standard 8' width. Cleaned out numerous badly silted drains. Reached the trail junction with the Old Boney Trail. The Fossil Trail is now complete. Stopped work and began hike back to the trail head. . Arrived back at the meeting place. Project complete. Total volunteer hours: 4 Volunteers x 6 hours = 24 hours Feet of trail maintained: 1,900 ft. CrewMembers: Jerry Mitcham Barry Dydyk Anne Russel Dave Perlmutter