Single Event Record Display
× Home Crew Stats-old version Trail Stats Work Schedule Agency Report by Years Crew- Year by Year Totals Crew- Stats - XTAB Crew Accomplishments
Event#:776
Date: 2020-12-12
Agency:State Parks
Trail: BBT Yerba Buena
Leader:Jerry Mitcham
Hours: 28
Volunteers:7
Distance:2200
Status: Completed
Regulars: 7
Casuals: 0
pdf:20201212BBT-YerbaBuena.pdf
CSUCI: 0
Tag:BBT, CIRCLE X
Previous Events
ID Date Leader Hours
7762020-12-12Jerry Mitcham28.0
Crew Member Hours
Anne Russell4.00
Barry Dydyk4.00
Dave Perlmutter4.00
Don Brusselars4.00
Jerry Mitcham4.00
Norm Simmonds4.00
Sharon Simmonds4.00
This was one of the specially scheduled COVID-19 trail maintenance projects. The goal of this project was to perform routine trail maintenance on the newest section of the BBT off Yerba Buena Road. We had 7 volunteers for the project. Met at the trail head on Yerba Buena Road. Began work at the trailhead. Used the power tool to trim brush back to the standard 6'-8' width. Cleaned out the inside drains at the switchbacks. Completed work on the entire section of trail. Had lunch and returned to the meeting place. . Arrived back at the meeting place. Project complete. Total volunteer hours: 7 Volunteers x 4 hours = 28 hours Feet of trail maintained: 2,200 ft. CrewMembers: Jerry Mitcham Barry Dydyk Anne Russel Dave Perlmutter Don Brusselars Norm Simmonds Sharon Simmonds