Single Event Record Display
× Home Crew Stats-old version Trail Stats Work Schedule Agency Report by Years Crew- Year by Year Totals Crew- Stats - XTAB Crew Accomplishments
Event#:799
Date: 2021-04-10
Agency:State Parks
Trail: Hidden Pond Trail
Leader:Jerry Mitcham
Hours: 24
Volunteers:4
Distance:1200
Status: Completed
Regulars: 4
Casuals: 0
pdf:20210410HiddenPondTrail.pdf
CSUCI: 0
Tag:PMSP
Previous Events
ID Date Leader Hours
8002021-04-17Jerry Mitcham30.0
7992021-04-10Jerry Mitcham24.0
7942021-03-27Jerry Mitcham48.0
7922021-03-20Jerry Mitcham30.0
7782020-12-19Jerry Mitcham36.0
7182020-01-18Don Brusselars45.0
7172020-01-15George Sherman48.0
7132020-01-04Barb Thomas90.0
7082019-11-30Dave Edwards45.0
7012019-10-26Dave Edwards48.0
6972019-10-09Norm Simmonds36.0
6922019-09-28Dave Edwards60.0
5612018-04-27Dave Edwards24.0
3022015-02-25Norm Simmonds48.0
2982015-02-18Norm Simmonds36.0
2922015-01-28Jerry Mitcham48.0
2912015-01-24Dave Edwards48.0
2892015-01-21Norm Simmonds48.0
2872015-01-14Norm Simmonds38.5
2822015-01-03Greg Sweel54.0
2732014-11-19Norm Simmonds48.0
1522013-06-2236.0
Crew Member Hours
Barry Dydyk6.00
Dave Perlmutter6.00
Don Brusselars6.00
Jerry Mitcham6.00
This was one of the specially scheduled COVID-19 trail maintenance projects. The goal of this project was to perform routine trail maintenance on the Hidden Pond Trail. We had 4 volunteers for the project. Met at the trail head at Wendy Drive and Potrero Road. Carpooled to the Hidden Pond connector trail head in on Sycamore Canyon Road. Began work. Used the power tool to trim brush back to the standard 8’ width. Performed maintenance on a total of.23 miles, which included.1 miles of tread work. Tread work consisted of slough removal, filling trench in trail and establishing an out slope to improve drainage.. Stopped work. Hiked back to the trail head, then carpooled back to the meeting place. . Arrived back at the meeting place. Project complete. Total volunteer hours: 4 Volunteers x 6 hours = 24 hours Feet of trail maintained: 1,200 ft.