Event#: | 861 |
Date: | 2022-03-02 |
Agency: | State Parks |
Trail: | Bent Arrow Trail |
Leader: | Dave Edwards |
Hours: | 36 |
Volunteers: | 6 |
Distance: | 100 |
Status: | Completed |
Regulars: | 6 |
Casuals: | 0 |
pdf: | 20220302BentArrowTrail.pdf |
CSUCI: | 0 |
Tag: | TSP |
Previous Events
ID |
Date |
Leader |
Hours |
861 | 2022-03-02 | Dave Edwards | 36.0 |
854 | 2022-02-16 | Dave Edwards | 30.0 |
859 | 2022-02-12 | Don Brusselars | 70.0 |
850 | 2022-02-05 | John Kross | 108.0 |
849 | 2022-01-29 | Dave Edwards | 174.0 |
842 | 2022-01-13 | Dave Edwards | 12.0 |
Crew Member |
Hours |
Dave Edwards | 6.00 |
Don Brusselars | 6.00 |
Jerry Mitcham | 6.00 |
John Kross | 6.00 |
Jon Sheldon | 6.00 |
Ruth Feldon | 6.00 |
Location: Bent Arrow trail, Topanga State Park Crew leader: Dave Edwards Summary: We met at 9:00 at the parking area at the end of Reseda Blvd and drove into Topanga State Park to the Bent Arrow trailhead. The last two rows of planks were installed which completed the wall construction. Gravel was added with dirt on top to smooth out the tread. We also installed 6 wooden steps, 6x6x30 inches, just below the wall at a sharp and steep switchback. Each step was secured in place with two rebar stakes. This now completes our work on the Bent Arrow trail, at least for the time being. The crew consisted of 6 SMMTC persons and 3 from State Parks, including Jason Finlay. We arrived back at the parking area at 3:00. Crew size: 6 Hours worked: 6 Total hours: 36 Total feet of trail worked: n/a Crew members: Dave Edwards, Jerry Mitcham, John Kross, Jon Sheldon, Ruth Feldon, Don Brusselars